Inspection assignment at Westinghouse

Westinghouse hired Semcon to work with the Vattenfall organization in order to optimize the work during the shutdown period of Ringhals reactor no. 2.

Semcon made continuous inspections of rebuilt and replaced electrical installations as part of the Twice project. The work included planning, coordination and continuous inspection of the cabinets, switchboards, cabling and installations.

In the Twice project 500 000 metres of new cable was rolled out in nearly 700 installation packages to monitor 27 000 signals in 360 new cabinets and panels.

Share

Contacts

Rickard Löfström

Rickard Löfström

Automation & Electrical design

+46 (0)736 84 04 00

rickard.lofstrom@semcon.com
Peter McKenzie-Midlane

Peter McKenzie-Midlane

Manager Energy, Power and Offshore

+44 (0) 7557 303 058

Peter.McKenzie-Midlane@semcon.com